06/12/08
Construction continues on Spurwink
Avenue, water main replacements scheduled for summer
Public Works Director Robert Malley has issued an update of construction
of activity that is, and will be, occurring in Cape Elizabeth in the coming
weeks:
Spurwink Avenue Reconstruction Project
The project continues to go well and on remain on schedule. The roadside
swales have been redefined and new drainage infrastructure has been added.
The surface has been reclaimed, which is a virtual "roto-tilling" of the
pavement and a portion of the gravel base to create a stronger foundation
for the new pavement. This week the road is being fine-graded to meet the
new design elevations, and accommodate a 3-foot wide paved shoulder on both
sides of the road.
This coming Tuesday, June 17, 2008, weather permitting, the surface will
be reclaimed again, which will be part of the "foamed asphalt" treatment.
During the reclaim procedure, liquid asphalt, water and dry cement is mixed
together with the existing surface to form a 4-inch thick base. This will
involve a 2,500-foot lane closure and delays as motorists are channled through
a one-way system. Motorists should seek an alternative route, such as Route
77 or Fowler Road, next week.
Once the foaming procedure is complete, which should take three days, the
base will be covered with two layers of pavement. The base pavement
is scheduled to be placed later this month, so the road will be much more
user friendly for the weekend of July 4.
The project should be wrapped up by the end of July. The Town is then going
to repave Spurwink Avenue from Deer Run Road to the Purpoodock Club the week
after Labor Day.
Water Main Replacements
The Portland Water District has contracted with the construction firm of
Maietta Construction to replace the water mains on Wheeler Road, Cragmoor
South and Summit Road. Work on Wheeler Road is scheduled for the latter part
of June. Cragmoor South is scheduled for the first week in July and Summit
Road is scheduled for the second week of July. The district will make the
necessary notifications regarding any shutdowns to customers impacted by
the water main replacements. Questions regarding any phase of this work should
be directed to Frank Meader, Utility Coordinator for the Portland Water District
at 774-5961 Ext. 3069. |